A guide for safe practices under the Renovation, Repair and Painting (RRP) Rule.

Renovation, repair and painting rule (RRP) requires the certified contractor to provide with lead-safe work practice to minimize any potential hazard that might emerge from these situations. Following this work practices under the Renovation, repair and painting rule (RRP) is a requirement of EPA’s rule and must be followed closely when completing a renovation, repair or painting any surface that has been identified with lead-based paint.

Checklist of Lead-Safe Work Practice under RRP
•    Hand in the EPA Lead pamphlet to the owner and occupant before starting the job.
•    Confirmation of receipt of the Lead Pamphlet must be received at least seven days before commencement
•    Limit Access to buildings occupant’s while working on the area.
•    Prepare a clean-up station, including paper towels, eye wash kits, first aid kits, potable water, etc.
•    Complete a pre-clean service on floors, windows, chairs, baseboard before protecting these items.
•    Protect all objects that were not removed with four mil protective sheeting. This sheeting must be properly secure in all sheeting borders.
•    Use a six mil protective sheeting to cover floors, carpets, including baseboard.
•    It is recommended to seal windows with protective sheeting.
•    HVAC ducts supply and returns grills must be closed and sealed with protective sheeting.
•    Create an airlock on door openings by sealing with two layers of protective sheeting, the first one with six mil plastic and the second one with – two or four mil plastic.
•    Set up a ‘dust room’ where you can work with high dust-generating components.
•    All tools, protective equipment and related items must be placed inside the protected areas.
•    Provide covering for outside ground at least ten feet away from the building. Never leave ground covering overnight.
•    For each additional story being worked out, you must extend ten feet of additional ground cover protection.
•    On high wind areas or gusty areas prepare a curb around the building to contain any particle that might be carried away.
•    Windows and doors on a 20 feet radius are recommended to be sealed and protected.
•    In some instance sheeting must be provided to scaffolding components.
•    Workers should remove Tyvek coveralls, booties, masks, etc. before leaving the work area 
•     Hepa mask must be removed from work area to prevent dust settling into it.
•    Follow local and state waste disposal regulations.
•    Trash bag or debris can be enclosed with a six mil protective sheeting.

Renovation, Repair and Painting Prohibited Removal Methods
EPA’s ruling must be followed closely, but these actions should be avoided:
•    Open flame burning 
•    Sanding/blasting without HEPA filter
•    Heat gun over 1,100 ° F 
•    Dry scraping or sanding
•    Paint strippers that contain Methylene Chloride
•    Do not use unconstrained hydro-blasting

Share on facebook
Share on google
Share on twitter
Share on linkedin
United Alliance service corporation logo.

United Alliance Corporate Office

United Alliance Pawtucket Office

Latest News

Categories

CONTACT US

Request A Quote For
Safety Training Or Consulting





Service Requested:

Requested Start Date of Service:


United Alliance Corporate Office

3119 Cranberry Hwy #5b

East Wareham, MA 02538

 

United Alliance Pawtucket Office


249 Roosevelt Ave, Suite 203

Pawtucket, RI 02860

Shopping Basket